| Task | Start | Finish |
| PREP SITE | 04/20/07 | 05/03/07 |
| Install Silt Fence | 04/20/07 | 04/26/07 |
| Inspect Silt Fence | 04/27/07 | 05/02/07 |
| Cut Trees | 04/20/07 | 04/24/07 |
| Grub and Stump | 04/25/07 | 04/27/07 |
| Stake House, Well, and Septic | 04/30/07 | 05/01/07 |
| Install Temporary Power | 05/02/07 | 05/02/07 |
| Dumpster and Port-o-Pottie | 05/02/07 | 05/02/07 |
| Add or Remove Fill | 05/02/07 | 05/03/07 |
| WELL | 05/04/07 | 05/17/07 |
| Drill Well | 05/04/07 | 05/07/07 |
| Quality and Quanity Test | 05/08/07 | 05/17/07 |
| Well Pump and Well Line to House | 05/04/07 | 05/04/07 |
| FOUNDATION | 05/18/07 | 06/14/07 |
| Excavate for Foundation | 05/18/07 | 05/21/07 |
| Footings, Walls and Sono Tubes | 05/22/07 | 05/25/07 |
| Foundation Tape Survey Certification | 05/28/07 | 05/28/07 |
| Damproofing | 05/29/07 | 05/29/07 |
| Perimeter Drains | 05/30/07 | 05/30/07 |
| Bulkhead | 05/31/07 | 05/31/07 |
| Install In-Floor Utilities | 06/01/07 | 06/04/07 |
| Inspect Foundation | 06/05/07 | 06/06/07 |
| Install Well Line | 06/07/07 | 06/07/07 |
| Backfill / Reinforce Walls / Install Decking | 06/08/07 | 06/11/07 |
| Pour Slab | 06/12/07 | 06/12/07 |
| Install Driveway Gravel | 06/13/07 | 06/14/07 |
| SANITARY SERVICES | 06/15/07 | 06/19/07 |
| Install Municipal Sewer Line | 06/15/07 | 06/19/07 |
| Install Municipal Water | 06/15/07 | 06/19/07 |
| FRAMING | 06/15/07 | 08/01/07 |
| Framing Material Delivery | 06/15/07 | 06/15/07 |
| Frame Out Building and Sheath | 06/18/07 | 07/27/07 |
| Install Tub and Shower Units | 07/30/07 | 08/01/07 |
| Build Decks | 07/30/07 | 08/01/07 |
| Handicap Ramps | 06/15/07 | 06/15/07 |
| CHIMNEY / FIREPLACE | 08/02/07 | 10/01/07 |
| Chimney Products Delivered | 08/02/07 | 09/12/07 |
| Install Chimney / Fireplace | 09/13/07 | 09/26/07 |
| Inspect Chimney and Firebox | 09/27/07 | 10/01/07 |
| ROOFING | 08/16/07 | 08/22/07 |
| Roof Material Delivery | 08/16/07 | 08/16/07 |
| Install Roofing | 08/17/07 | 08/22/07 |
| WINDOWS AND DOORS | 08/23/07 | 09/19/07 |
| Install Windows | 08/23/07 | 09/19/07 |
| Install Doors | 08/23/07 | 09/19/07 |
| EXTERIOR FINISH | 09/20/07 | 09/26/07 |
| Materials On Site | 09/20/07 | 09/20/07 |
| Install Exterior Finish | 09/20/07 | 09/26/07 |
| ROUGH HVAC | 08/02/07 | 08/07/07 |
| Rough-in Heating and Cooling | 08/02/07 | 08/06/07 |
| Rough Inspection | 08/07/07 | 08/07/07 |
| ROUGH PLUMBING | 08/02/07 | 08/17/07 |
| Plumbing Permit | 08/02/07 | 08/02/07 |
| Ensure Adaptations are Considered | 08/02/07 | 08/02/07 |
| Rough-in Plumbing | 08/03/07 | 08/06/07 |
| Rough-in Central Vac | 08/03/07 | 08/06/07 |
| Rough Inspection | 08/07/07 | 08/17/07 |
| ROUGH ELECTRICAL | 08/02/07 | 10/12/07 |
| Pull Permit | 08/02/07 | 08/02/07 |
| Ensure Adaptations are Considered | 08/02/07 | 08/02/07 |
| Rough-in Electrical | 08/03/07 | 10/11/07 |
| Rough Inspection | 10/12/07 | 10/12/07 |
| INSULATE WALLS | 10/15/07 | 10/17/07 |
| Draft Stopping and Fire Blocking | 10/15/07 | 10/15/07 |
| Inspection Prior to Insulation | 10/16/07 | 10/16/07 |
| Install Insulation | 10/15/07 | 10/16/07 |
| Inspection After Insulation | 10/17/07 | 10/17/07 |
| PLASTER / DRYWALL | 10/18/07 | 10/19/07 |
| Material Delivery | 10/18/07 | 10/18/07 |
| Board and Plaster | 10/19/07 | 10/19/07 |
| FINISH CARPENTRY AND MILLWORK | 10/22/07 | 10/26/07 |
| Material Delivery | 10/22/07 | 10/22/07 |
| Install Harwood Floors | 10/23/07 | 10/26/07 |
| Install Underlayment | 10/23/07 | 10/25/07 |
| Install Cabinets and Vanities | 10/23/07 | 10/25/07 |
| Install Interior Millwork and Trim | 10/23/07 | 10/26/07 |
| PAINTING | 10/29/07 | 11/02/07 |
| Material Delivery | 10/29/07 | 10/29/07 |
| Paint Walls, Celings and Trim | 10/30/07 | 11/02/07 |
| FINISH PLUMBING | 10/29/07 | 10/29/07 |
| Material Delivery | 10/29/07 | 10/29/07 |
| Install Finish Plumbing | 10/29/07 | 10/29/07 |
| Final Inspection | 10/29/07 | 10/29/07 |
| FLOORING | 10/29/07 | 11/02/07 |
| Material Delivery | 10/29/07 | 10/29/07 |
| Install Tile | 10/30/07 | 11/02/07 |
| Install Vinyl | 10/30/07 | 10/30/07 |
| Install Carpet | 10/30/07 | 10/31/07 |
| Protect Flooring / Booties on Site | 10/29/07 | 10/29/07 |
| FINISH ELECTRICAL | 11/05/07 | 11/05/07 |
| Material Delivery | 11/05/07 | 11/05/07 |
| Install Finish Wire and Fixtures | 11/05/07 | 11/05/07 |
| Finish Electrical Inspection | 11/05/07 | 11/05/07 |
| FINISH HVAC | 11/06/07 | 11/06/07 |
| Material Delivery | 11/06/07 | 11/06/07 |
| Install Finish HVAC | 11/06/07 | 11/06/07 |
| HVAC Inspection | 11/06/07 | 11/06/07 |
| FINISH INSULATION | 11/07/07 | 11/07/07 |
| Insulate Attic | 11/07/07 | 11/07/07 |
| Insulate Basement Ceiling | 11/07/07 | 11/07/07 |
| DRIVEWAY AND LANDSCAPING | 11/05/07 | 11/16/07 |
| Pave Driveway | 11/05/07 | 11/05/07 |
| Pave Walkways | 11/05/07 | 11/07/07 |
| Install Irrigation System | 11/05/07 | 11/09/07 |
| Loam, Rake and Seed and/or Sod | 11/12/07 | 11/16/07 |
| Plant Shrubs and Mulch Gardens | 11/05/07 | 11/07/07 |
| Install Fencing | 11/05/07 | 11/05/07 |
| Install Downspouts and Gutters | 11/05/07 | 11/05/07 |
| FINAL INSPECTIONS | 11/27/07 | 12/10/07 |
| SAH / VA Inspection | 11/27/07 | 12/10/07 |
| Smokes Cert / Carbes cert | 11/27/07 | 12/05/07 |
| Install Permanent Flagpole | 11/27/07 | 11/28/07 |
| BLR / FO PERMIT | 11/27/07 | 11/27/07 |
| Remove Dumpster | 11/27/07 | 11/27/07 |
| Certificate of Compliance | 12/06/07 | 12/06/07 |
| Punch List Items | 12/07/07 | 12/10/07 |
| Certificate of Occupancy | 12/07/07 | 12/07/07 |