| PREP SITE | 5-Jan-07 | 18-Jan-07 |
| Install Silt Fence | 5-Jan-07 | 11-Jan-07 |
| Inspect Silt Fence | 12-Jan-07 | 17-Jan-07 |
| Cut Trees | 5-Jan-07 | 9-Jan-07 |
| Grub and Stump | 10-Jan-07 | 12-Jan-07 |
| Stake House, Well, and Septic | 15-Jan-07 | 16-Jan-07 |
| Install Temporary Power | 17-Jan-07 | 17-Jan-07 |
| Dumpster and Port-o-Pottie | 17-Jan-07 | 17-Jan-07 |
| Add or Remove Fill | 17-Jan-07 | 18-Jan-07 |
| FOUNDATION | 19-Jan-07 | 22-Mar-07 |
| Excavate for Foundation | 19-Jan-07 | 1-Feb-07 |
| Footings, Walls and Sono Tubes | 23-Jan-07 | 16-Feb-07 |
| Foundation Tape Survey Certification | 19-Feb-07 | 23-Feb-07 |
| Damproofing | 26-Feb-07 | 26-Feb-07 |
| Perimeter Drains | 27-Feb-07 | 27-Feb-07 |
| Bulkhead | 28-Feb-07 | 28-Feb-07 |
| Install In-Floor Utilities | 1-Mar-07 | 2-Mar-07 |
| Inspect Foundation | 5-Mar-07 | 6-Mar-07 |
| Install Well Line | 7-Mar-07 | 7-Mar-07 |
| Backfill / Reinforce Walls / Install Decking | 8-Mar-07 | 21-Mar-07 |
| Pour Slab | 22-Mar-07 | 22-Mar-07 |
| Install Driveway Gravel | 2-Feb-07 | 5-Feb-07 |
| SANITARY SERVICES | 16-Feb-07 | 20-Feb-07 |
| Install Municipal Sewer Line | 16-Feb-07 | 20-Feb-07 |
| Install Municipal Water | 16-Feb-07 | 20-Feb-07 |
| FRAMING | 22-Feb-07 | 16-Apr-07 |
| Framing Material Delivery | 23-Mar-07 | 23-Mar-07 |
| Frame Out Building and Sheath | 22-Feb-07 | 11-Apr-07 |
| Install Tub and Shower Units | 12-Apr-07 | 16-Apr-07 |
| CHIMNEY / FIREPLACE | 5-Jan-07 | 18-Jan-07 |
| Chimney Products Delivered | 5-Jan-07 | 5-Jan-07 |
| Install Chimney / Fireplace | 8-Jan-07 | 16-Jan-07 |
| Inspect Chimney and Firebox | 17-Jan-07 | 18-Jan-07 |
| ROOFING | 2-May-07 | 8-May-07 |
| Roof Material Delivery | 2-May-07 | 2-May-07 |
| Install Roofing | 3-May-07 | 8-May-07 |
| WINDOWS AND DOORS | 9-May-07 | 15-May-07 |
| Install Windows | 9-May-07 | 15-May-07 |
| Install Doors | 9-May-07 | 15-May-07 |
| EXTERIOR FINISH | 16-May-07 | 6-Jul-07 |
| Materials On Site | 16-May-07 | 16-May-07 |
| Install Exterior Finish | 1-Jul-07 | 6-Jul-07 |
| ROUGH HVAC | 14-Mar-07 | 7-May-07 |
| Rough-in Heating and Cooling | 14-Mar-07 | 3-May-07 |
| Special HVAC Prep and Install | 4-May-07 | 4-May-07 |
| Rough Inspection | 7-May-07 | 7-May-07 |
| ROUGH PLUMBING | 18-Apr-07 | 18-May-07 |
| Plumbing Permit | 18-Apr-07 | 18-Apr-07 |
| Ensure Adaptations are Considered | 18-Apr-07 | 18-Apr-07 |
| Rough-in Plumbing | 19-Apr-07 | 16-May-07 |
| Rough-in Central Vac | 19-Apr-07 | 20-Apr-07 |
| Rough Inspection | 17-May-07 | 18-May-07 |
| ROUGH ELECTRICAL | 8-May-07 | 6-Jun-07 |
| Pull Permit | 8-May-07 | 8-May-07 |
| Ensure Adaptations are Considered | 8-May-07 | 11-May-07 |
| Rough-in Electrical | 9-May-07 | 5-Jun-07 |
| Rough-in Alarm | 9-May-07 | 9-May-07 |
| Rough Inspection | 6-Jun-07 | 6-Jun-07 |
| INSULATE WALLS | 7-Jun-07 | 13-Jun-07 |
| Draft Stopping and Fire Blocking | 7-Jun-07 | 7-Jun-07 |
| Inspection Prior to Insulation | 8-Jun-07 | 8-Jun-07 |
| Install Insulation | 7-Jun-07 | 12-Jun-07 |
| Inspection After Insulation | 13-Jun-07 | 13-Jun-07 |
| PLASTER / DRYWALL | 18-Jul-07 | 25-Jul-07 |
| Material Delivery | 18-Jul-07 | 18-Jul-07 |
| Board and Plaster | 19-Jul-07 | 25-Jul-07 |
| FINISH CARPENTRY AND MILLWORK | 26-Jul-07 | 1-Aug-07 |
| Material Delivery | 26-Jul-07 | 26-Jul-07 |
| Install Harwood Floors | 27-Jul-07 | 1-Aug-07 |
| Install Underlayment | 27-Jul-07 | 31-Jul-07 |
| Install Cabinets and Vanities | 27-Jul-07 | 31-Jul-07 |
| Install Interior Millwork and Trim | 27-Jul-07 | 1-Aug-07 |
| PAINTING | 2-Aug-07 | 8-Aug-07 |
| Material Delivery | 2-Aug-07 | 2-Aug-07 |
| Paint Walls, Celings and Trim | 3-Aug-07 | 8-Aug-07 |
| FINISH PLUMBING | 2-Aug-07 | 29-Aug-07 |
| Material Delivery | 2-Aug-07 | 2-Aug-07 |
| Install Finish Plumbing | 2-Aug-07 | 29-Aug-07 |
| Final Inspection | 2-Aug-07 | 2-Aug-07 |
| FLOORING | 2-Aug-07 | 6-Sep-07 |
| Material Delivery | 2-Aug-07 | 2-Aug-07 |
| Install Tile | 3-Aug-07 | 6-Sep-07 |
| Install Vinyl | 3-Aug-07 | 6-Sep-07 |
| Install Carpet | 3-Aug-07 | 6-Sep-07 |
| Protect Flooring / Booties on Site | 2-Aug-07 | 6-Sep-07 |
| FINISH ELECTRICAL | 9-Aug-07 | 12-Sep-07 |
| Material Delivery | 9-Aug-07 | 6-Sep-07 |
| Install Finish Wire and Fixtures | 9-Aug-07 | 6-Sep-07 |
| Finish Electrical Inspection | 9-Aug-07 | 12-Sep-07 |
| FINISH HVAC | 13-Sep-07 | 26-Sep-07 |
| Material Delivery | 13-Sep-07 | 26-Sep-07 |
| Install Finish HVAC | 13-Sep-07 | 26-Sep-07 |
| HVAC Inspection | 13-Sep-07 | 26-Sep-07 |
| FINISH INSULATION | 27-Sep-07 | 27-Sep-07 |
| Insulate Attic | 27-Sep-07 | 27-Sep-07 |
| Insulate Basement Ceiling | 27-Sep-07 | 27-Sep-07 |
| DRIVEWAY AND LANDSCAPING | 7-Sep-07 | 28-Sep-07 |
| Pave Driveway | 7-Sep-07 | 18-Sep-07 |
| Pave Walkways | 7-Sep-07 | 18-Sep-07 |
| Install Irrigation System | 7-Sep-07 | 18-Sep-07 |
| Loam, Rake and Seed and/or Sod | 19-Sep-07 | 28-Sep-07 |
| Plant Shrubs and Mulch Gardens | 7-Sep-07 | 18-Sep-07 |
| Install Fencing | 7-Sep-07 | 18-Sep-07 |
| Install Downspouts and Gutters | 7-Sep-07 | 18-Sep-07 |
| FINAL INSPECTIONS | 28-Sep-07 | 5-Oct-07 |
| SAH / VA Inspection | 28-Sep-07 | 5-Oct-07 |
| Smokes Cert / Carbes cert | 28-Sep-07 | 2-Oct-07 |
| Install Permanent Flagpole | 28-Sep-07 | 1-Oct-07 |
| BLR / FO PERMIT | 28-Sep-07 | 28-Sep-07 |
| Remove Dumpster | 28-Sep-07 | 28-Sep-07 |
| Certificate of Compliance | 3-Oct-07 | 3-Oct-07 |
| Punch List Items | 4-Oct-07 | 5-Oct-07 |
| Certificate of Occupancy | 4-Oct-07 | 4-Oct-07 |
| DEED TRANSFER | 8-Oct-07 | 8-Oct-07 |